CSO Projects

CSO Project Milestones
In July 2001, the EPA and state EPD approved the City’s plan to eliminate water quality violations from CSOs. The City’s approved plan was to construct a CSO tunnel and sewer separation of selected sewer areas. This would improve water quality in our local streams and creeks by reducing the number of CSOs.
Project | Construction Cost* | Notice to Proceed | Substantial Completion |
---|---|---|---|
West Area CSO Control Facilities | $4,328,045 | December 2004 | February 2006 |
Custer Avenue Storage & Dechlorination Facility | $36,700,000 | February 2005 | November 2006 |
Intrenchment Creek CSO Water Quality Control Facility | $28,606,000 | February 2005 | January 2007 |
Greenway Acquisition | $25,000,000 | January 2001 | March 2007 |
McDaniel Basin Sewer Separation | $85,424,090 | April 2005 | August 2007 |
Stockade Basin Sewer Separation | $79,630,400 | April 2005 | August 2007 |
Greensferry Basin Sewer Separation | $92,835,221 | July 2005 | September 2007 |
West Area Water Quality Control Facility | $47,293,314 | September 2005 | October 2007 |
West Area CSO Tunnel | $210,231,000 | July 2004 | October 2008 |
Total Cost to Construct | $610,048,070 |